Marktredwitz - municipal local heating supply

Haag and Hammerberg are districts of the town of Marktredwitz and are to be supplied with local heating. The area under consideration consists of about 5 existing properties and a planned new development area with about 50 plots and predominantly single-family houses.

The heat is obtained from the waste heat of an existing biogas plant on the outskirts of the village, including a natural gas peak load boiler, and is fed into the pipeline network by the plant operator at the beginning. To distribute the heat, a heating network was constructed with PMR pipes, which are flexible composite pipes with a medium pipe made of plastic. The pipeline network comprises about 2,000 metres and was constructed using a double-pipe system.

Key data on the project

Municipal enterprise Marktredwitz

Marktredwitz is a town in the district of Wunsiedel im Fichtelgebirge with about 17,000 inhabitants and is located in the administrative district of Upper Franconia.

Industrial sector

Municipalities and communities

Project location

Marktredwitz

Target group

Municipalities and heating network operators

Keywords

Heat network, local heating, heat network, CO2 savings, planning, tendering, biogas, heat generation

Customer benefits

Qualified planning services for the construction of a local heating network and enabling successful implementation

Scope of services

eta Energieberatung was commissioned for an initial analysis as well as for the planning services for the local heating pipes and transfer stations according to HOAI (Fee Structure for Architects and Engineers). The scope of services essentially refers to:

  • Carrying out the initial analysis
    Plausibility check of the heat demand
    Simulation of an annual duration curve incl. representation of biogas heat
    Quantification of heat supply from biogas and peak load boiler
    Pre-dimensioning of the heat pipes
    Determination of network length and expected network losses
    Comparison of the advantages of KMR and PMR pipeline systems in relation to the project
    Calculation of economic efficiency
    Presentation of results
  • Design planning
    Drawing up a design on the basis of the preliminary planning.
    Dimensioning of the local heating network, coordination with third parties
    Cost calculation and preparation of a cost plan
    Summary
  • Implementation planning
    Development of the implementation planning
    Drawing representation
  • Providing the results of the work
    Summary
  • Preparation of the award
    Compilation of the tender documents
    Functional tendering for local heating network
    Compilation of the tender documents
  • Participation in the awarding
    Obtaining offers
    Checking and evaluating the offers
    Drawing up the price comparison list
    Preparing the award proposal
  • Object supervision (construction supervision)
    Supervision of local construction supervision
    Participation in the acceptance
  • Object supervision and documentation
    Documentation review
    Participation in the release of security deposits
    Contributing to the systematic compilation of the drawing representation and arithmetical results of the object

We help you to realise your concepts!

We would be happy to advise you on the planning of your heating and accommodation concepts. In doing so, we will also tell you what specific opportunities you have to take advantage of the corresponding subsidy programmes. 

Together with you, we will then also implement the concept.

Call me without obligation or send me an e-mail.

Kathrin Merkert

Success message!

Warning message!